Q1. The reasons which are basically responsible for the formation of a queue should be that
(A) the average service rate Hess than the average arrival rate
(B) output rate is linearly proportional to input
(C) output rate is constant and the input varies in a random manner
(D) All of these
Answer: All of these
Explanation:
Q2. Queuing theory is associated with
(A) sales
(B) inspection time
(C) waiting time
(D) production time
Answer: waiting time
Explanation:
Q3. In queuing theory, the nature of the waiting situation can be studied and analysed mathematically if
(A) complete details’of items in, waiting line are known
(B) arrival and waiting times are known and can be grouped to form a waiting line model
(C) all variables and constants are known and form a linear equation
(D) the laws governing arrivals, service times, and the order in which the arriving units are taken into source are known
Answer: the laws governing arrivals, service times, and the order in which the arriving units are taken into source are known
Explanation:
Q4. Queuing theory is used for
(A) inventory problems
(B) traffic congestion studies
(C) job-shop scheduling
(D) All of these
Answer: All of these
Explanation:
Q5. The basic difference between PERT and CPM is that
(A) PERT deals with events and CPM with activities
(B) critical path is determined in PERT only
(C) costs are considered on CPM only and not in PERT
(D) guessed times are used in PERT and evaluated times in CPM
Answer: guessed times are used in PERT and evaluated times in CPM
Explanation:
Q6. PERT is the
(A) time oriented technique
(B) event oriented technique
(C) activity oriented technique
(D) target oriented technique
Answer: event oriented technique
Explanation:
Q7. Which of the following equations is not in conformity with others
(A) organisation performance x motivation = profits
(B) knowledge x skill = ability
(C) ability x motivation = performance
(D) attitude x situation = motivation
Answer: organisation performance x motivation = profits
Explanation:
Q8. Work study comprises following main techniques
(A) method study and work measurement
(B) method study and time study
(C) time study and work measurement
(D) method study and job evaluation
Answer: method study and work measurement
Explanation:
Q9. PMTP (predetermined motion time systems) include
(A) MTM (method time measurement)
(B) WFS (work factor systems)
(C) BNTS (basic motion time study)
(D) All of these
Answer: All of these
Explanation:
Q10. CPM is the
(A) time oriented technique
(B) event oriented technique
(C) activity oriented technique
(D) target oriented technique
Answer: activity oriented technique
Explanation:
Q11. A big advantage of PERT over Gantt charts is that in the former case
(A) activities and events are clearly shown
(B) early start and late finish of an activity are clearly marked
(C) critical path can be easily determined
(D) inter-relationship among activities is clearly shown
Answer: inter-relationship among activities is clearly shown
Explanation:
Q12. PERT and CPM are
(A) techniques to determine project status
(B) charts which increase aesthetic appearance of rooms
(C) aids to determine cost implications of project
(D) aids to the decision maker
Answer: aids to the decision maker
Explanation:
Q13. Slack represents the difference between the
(A) latest allowable time and the earliest expected time
(B) proposed allowable time and the earliest expected time
(C) normal allowable time and the latest expected time
(D) project initiation tune and actual starting time
Answer: latest allowable time and the earliest expected time
Explanation:
Q14. Bin card is used in
(A) administrative wing
(B) workshop
(C) foundry shop
(D) stores
Answer: stores
Explanation:
Q15. Which of the following depreciation system ensures that the interest be charged on the cost of machine asset every year on the book value, but the rate of depreciation every year remains constant
(A) sinking fund method
(B) straight line method
(C) A-B-C charging method
(D) annuity charging method
Answer: annuity charging method
Explanation:
Q16. String diagram is used
(A) for checking the relative values of various layouts
(B) when a group of workers are working at a place
(C) where processes require the operator to be moved from one place to another
(D) All of these
Answer: All of these
Explanation:
Q17. Replacement studies are made on the fol-lowing basis:
(A) annual cost method
(B) rate of return method
(C) present worth method
(D) any one of the above
Answer: any one of the above
Explanation:
Q18. The time required to complete a job is established and a bonus is paid to the worker based on the exact percentage of time saved. This type of incentive plan is known as
(A) Dry work Plan
(B) Halsey Premium Plan
(C) Taylor Plan
(D) Rowan Plan
Answer: Rowan Plan
Explanation:
Q19. The two-bin system is concerned with
(A) ordering procedure
(B) forecasting sales
(C) production planning
(D) despatching and expediting
Answer: ordering procedure
Explanation:
Q20. The simplex method is the basic method for
(A) value analysis
(B) operation research
(C) linear programming
(D) model analysis
Answer: linear programming
Explanation:
Related Multiple choice questions:
automobile engineering objective questions and answers part1
automobile engineering objective questions and answers part2
automobile engineering objective questions and answers part3
basic of mechanical engineering objective questions and answers part1
basic of mechanical engineering objective questions and answers part2
basic of mechanical engineering objective questions and answers part3
basic of mechanical engineering objective questions and answers part4
basic of mechanical engineering objective questions and answers part5
basic of mechanical engineering objective questions and answers part6
engineering materials objective questions and answers part1
engineering materials objective questions and answers part2
engineering materials objective questions and answers part3
engineering materials objective questions and answers part4
engineering materials objective questions and answers part5
engineering materials objective questions and answers part6
engineering materials objective questions and answers part7
engineering materials objective questions and answers part8
engineering materials objective questions and answers part9
engineering mechanics objective questions and answers part1
engineering mechanics objective questions and answers part2
engineering mechanics objective questions and answers part3
engineering mechanics objective questions and answers part4
fluid mechanics objective questions and answers part1
fluid mechanics objective questions and answers part2
fluid mechanics objective questions and answers part3
fluid mechanics objective questions and answers part4
fluid mechanics objective questions and answers part5
fluid mechanics objective questions and answers part6
fluid mechanics objective questions and answers part7
fluid mechanics objective questions and answers part8
fluid mechanics objective questions and answers part9
fluid mechanics objective questions and answers part10
fluid mechanics objective questions and answers part11
heat transfer objective questions and answers part1
heat transfer objective questions and answers part2
heat transfer objective questions and answers part3
heat transfer objective questions and answers part4
hydraulic machines objective questions and answers part1
hydraulic machines objective questions and answers part2
ic engines objective questions and answers part1
ic engines objective questions and answers part2
ic engines objective questions and answers part3
ic engines objective questions and answers part4
ic engines objective questions and answers part5
machine design objective questions and answers part1
machine design objective questions and answers part2
machine design objective questions and answers part3
machine design objective questions and answers part4
machine design objective questions and answers part5
machine design objective questions and answers part6
machine design objective questions and answers part7
production engineering objective questions and answers part1
production engineering objective questions and answers part2
production engineering objective questions and answers part3
production engineering objective questions and answers part4
production engineering objective questions and answers part5
production engineering objective questions and answers part6
production engineering objective questions and answers part7
production engineering objective questions and answers part8
production engineering objective questions and answers part9
steam engines objective questions and answers part1
steam engines objective questions and answers part2
steam engines objective questions and answers part3
steam engines objective questions and answers part4
steam engines objective questions and answers part5
steam engines objective questions and answers part6
steam engines objective questions and answers part7
steam engines objective questions and answers part8
steam engines objective questions and answers part9
strength of materials objective questions and answers part1
strength of materials objective questions and answers part2
strength of materials objective questions and answers part3
strength of materials objective questions and answers part4
theory of machines objective questions and answers part1
theory of machines objective questions and answers part2
theory of machines objective questions and answers part3
theory of machines objective questions and answers part4
theory of machines objective questions and answers part5
theory of machines objective questions and answers part6
theory of machines objective questions and answers part7
thermodynamics objective questions and answers part1
thermodynamics objective questions and answers part2
More Multiple choice questions:
Computer Science multiple choice questions and answers
Computer Science multiple choice questions and answers
Computer Science multiple choice questions and answers