Q1. Emergency rush order can be pushed more effectively in
(A) job production
(B) automatic production
(C) continuous production
(D) intermittent production
Answer: intermittent production
Explanation:
Q2. Routing assists engineers in deciding in advance
(A) the flow of material in the plant
(B) the methods of proper utilization of manpower
(C) the methods of proper utilization of machines
(D) the layout of factory facilities
Answer: the methods of proper utilization of machines
Explanation:
Q3. The performance of a specific task in CPM is known as
(A) dummy
(B) event
(C) activity
(D) contract
Answer: activity
Explanation:
Q4. Select the incorrect statement from the following
(A) an activity of the project is denoted by an arrow on the net work
(B) the tail of the arrow indicates the start of the activity
(C) the head of the arrow indicates the end of,the activity!
(D) the arrows are drawn (to scale from) left to right
Answer: the arrows are drawn (to scale from) left to right
Explanation:
Q5. The artificial activity; which indicates that an activity following it cannot be started unless, the preceding activity is complete, is known as
(A) event
(B) artificial
(C) constraint
(D) dummy
Answer: dummy
Explanation:
Q6. A dummy activity
(A) is artificially introduced
(B) is represented by a dotted line
(C) does not require any time
(D) All of these
Answer: All of these
Explanation:
Q7. The difference between the time available to do the job and the time required to do the job, is known as
(A) event
(B) float
(C) duration
(D) constraint
Answer: float
Explanation:
Q8. The probability distribution of activity times in PERT follows following distribution
(A) normal
(B) binomial
(C) beta
(D) exponential
Answer: beta
Explanation:
Q9. The probability distribution of project completion in PERT follows following distribution
(A) normal
(B) binomial
(C) exponential
(D) Gaussian
Answer: Gaussian
Explanation:
Q10. If TL is the largest allowable event occurrence time, total activity slack (s) is equal to
(A) latest start time – earliest start time
(B) latest finish time – earliest finish time (EFT)
(C) TL-EFT
(D) All of these
Answer: All of these
Explanation:
Q11. The critical activity has
(A) maximum float
(B) minimum float
(C) zero float
(D) average float
Answer: zero float
Explanation:
Q12. The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is Known as
(A) duration
(B) total float
(C) free float
(D) interfering float
Answer: free float
Explanation:
Q13. The critical path of a network represents
(A) the minimum time required for completion of project
(B) the maximum time required for completion of project
(C) maximum cost required for completion of project
(D) minimum cost required for completion of project
Answer: the minimum time required for completion of project
Explanation:
Q14. Select the correct statement from the following
(A) the float may be positive, zero or negative
(B) if the float is positive and the activity is delayed by a period equal to its total float, the completion of project in not delayed
(C) if the float of an activity is negative, delay in its performance is bound to delay the completion of project
(D) All of these
Answer: All of these
Explanation:
Q15. Critical path moves along the activities having total float of
(A) positive value
(B) negative value
(C) zero value
(D) same value
Answer: zero value
Explanation:
Q16. Critical Path Net Work helps an engineer
(A) to concentrate his attention on critical activities
(B) to divert the resources from non-critical advanced activities to critical activities
(C) to be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
(D) All of these
Answer: All of these
Explanation:
Q17. Select the correct statement about relationship between various floats
(A) free float = total float
(B) independent float > free float
(C) free float > total float
(D) independent float < free float.
Answer: independent float < free float.
Explanation:
Q18. The time which results in the least possible direct cost of an activity is known as
(A) normal time
(B) slow time
(C) crash time
(D) standard time
Answer: slow time
Explanation:
Q19. The technique for establishing and maintaining priorities among the various jobs of any project is known as
(A) event flow scheduling technique
(B) critical ratio scheduling
(C) slotting technique for scheduling
(D) short interval scheduling
Answer: critical ratio scheduling
Explanation:
Q20. PERT is
(A) limit up of event oriented diagrams
(B) used for research and development projects
(C) based on three time estimates for activities linking up two events
(D) All of these
Answer: All of these
Explanation:
Q21. CPMis
(A) synthesising in concepts
(B) is built of activities oriented program-mes
(C) is used for repetitive works
(D) All of these
Answer: All of these
Explanation:
Q22. A CPM family includes
(A) CPP (Critical Path Plotted)
(B) MCE (Minimum Cost Expenditure)
(C) CPS (Critical Path Scheduling)
(D) All of these
Answer: All of these
Explanation:
Q23. PERT/CPM, techniques can be used for following applications
(A) maintenance jobs
(B) research and development
(C) all non-technical jobs
(D) All of these
Answer: All of these
Explanation:
Q24. PERT analysis is based on
(A) optimistic time
(B) pessimistic time
(C) most likely time
(D) All of these
Answer: All of these
Explanation:
Q25. Discrepancies of bar chart techniques are
(A) consequential effects of lack in one activity on omer
(B) consequential effects of lack in one activity on the finish date
(C) free time available for an activity can’t be predicted
(D) All of these
Answer: All of these
Explanation:
Related Multiple choice questions:
automobile engineering objective questions and answers part1
automobile engineering objective questions and answers part2
automobile engineering objective questions and answers part3
basic of mechanical engineering objective questions and answers part1
basic of mechanical engineering objective questions and answers part2
basic of mechanical engineering objective questions and answers part3
basic of mechanical engineering objective questions and answers part4
basic of mechanical engineering objective questions and answers part5
basic of mechanical engineering objective questions and answers part6
engineering materials objective questions and answers part1
engineering materials objective questions and answers part2
engineering materials objective questions and answers part3
engineering materials objective questions and answers part4
engineering materials objective questions and answers part5
engineering materials objective questions and answers part6
engineering materials objective questions and answers part7
engineering materials objective questions and answers part8
engineering materials objective questions and answers part9
engineering mechanics objective questions and answers part1
engineering mechanics objective questions and answers part2
engineering mechanics objective questions and answers part3
engineering mechanics objective questions and answers part4
fluid mechanics objective questions and answers part1
fluid mechanics objective questions and answers part2
fluid mechanics objective questions and answers part3
fluid mechanics objective questions and answers part4
fluid mechanics objective questions and answers part5
fluid mechanics objective questions and answers part6
fluid mechanics objective questions and answers part7
fluid mechanics objective questions and answers part8
fluid mechanics objective questions and answers part9
fluid mechanics objective questions and answers part10
fluid mechanics objective questions and answers part11
heat transfer objective questions and answers part1
heat transfer objective questions and answers part2
heat transfer objective questions and answers part3
heat transfer objective questions and answers part4
hydraulic machines objective questions and answers part1
hydraulic machines objective questions and answers part2
ic engines objective questions and answers part1
ic engines objective questions and answers part2
ic engines objective questions and answers part3
ic engines objective questions and answers part4
ic engines objective questions and answers part5
machine design objective questions and answers part1
machine design objective questions and answers part2
machine design objective questions and answers part3
machine design objective questions and answers part4
machine design objective questions and answers part5
machine design objective questions and answers part6
machine design objective questions and answers part7
production engineering objective questions and answers part1
production engineering objective questions and answers part2
production engineering objective questions and answers part3
production engineering objective questions and answers part4
production engineering objective questions and answers part5
production engineering objective questions and answers part6
production engineering objective questions and answers part7
production engineering objective questions and answers part8
production engineering objective questions and answers part9
steam engines objective questions and answers part1
steam engines objective questions and answers part2
steam engines objective questions and answers part3
steam engines objective questions and answers part4
steam engines objective questions and answers part5
steam engines objective questions and answers part6
steam engines objective questions and answers part7
steam engines objective questions and answers part8
steam engines objective questions and answers part9
strength of materials objective questions and answers part1
strength of materials objective questions and answers part2
strength of materials objective questions and answers part3
strength of materials objective questions and answers part4
theory of machines objective questions and answers part1
theory of machines objective questions and answers part2
theory of machines objective questions and answers part3
theory of machines objective questions and answers part4
theory of machines objective questions and answers part5
theory of machines objective questions and answers part6
theory of machines objective questions and answers part7
thermodynamics objective questions and answers part1
thermodynamics objective questions and answers part2
More Multiple choice questions:
Computer Science multiple choice questions and answers
Computer Science multiple choice questions and answers
Computer Science multiple choice questions and answers