Q1. O on a PERT/CPM chart represents
(A) an ordinary event
(B) a significant event representing some mile-stone
(C) an event to be transferred to other network chart
(D) dangling event
Answer: an ordinary event
Explanation:
Q2. Select the correct statement. Dummy activity on a PERT/CPM chart means, it
(A) consumes time, but no resources
(B) consumes resources but no time
(C) consumes neither time nor resources
(D) is a dangling event
Answer: consumes neither time nor resources
Explanation:
Q3. Critical path on PERT/CPM chart is obtained by joining the events having
(A) maximum slack
(B) minimum slack
(C) average slack
(D) no slack
Answer: minimum slack
Explanation:
Q4. Slack of various events on the critical path in PERT/CPM chart
(A) increases continuously
(B) decreases continuously
(C) remains constant
(D) may increase or decrease depending on various factors
Answer: remains constant
Explanation:
Q5. The assumption in PERT is
(A) a project will always be behind schedule, if left uncorrected
(B) cost of project will always be more than the estimated cost, if no timely corrections are taken
(C) a project can be subdivided into a set of predictable, independent activities
(D) activities are fixed and can’t be changed ,
Answer: a project can be subdivided into a set of predictable, independent activities
Explanation:
Q6. Activity s,lack or float of any event on a PERT/CPM chart is represented by
(A) latest start time of succeeding event -earliest finish time of preceding event activity time
(B) latest start time of the event – earliest start time of the event
(C) latest finish time of event – earliest finish time of the event
(D) anyone of the above
Answer: anyone of the above
Explanation:
Q7. The important file in making a PERT is
(A) an event can’t be accomplished until activities leading to it are completed
(B) length of arrow has nothing to do with time
(C) every activity must be completed before end point is reached
(D) All of these
Answer: All of these
Explanation:
Q8. An event is indicated on the network by
(A) a straight line
(B) a number enclosed in a circle or a square
(C) a straight line with circles at the ends
(D) a dotted line
Answer: a number enclosed in a circle or a square
Explanation:
Q9. In a PERT chart
(A) all activities should be numbered
(B) only important activities should be numbered
(C) only critical activities are numbered
(D) only selected activities are numbered
Answer: all activities should be numbered
Explanation:
Q10. Positive slack on a PERT indicates that project is
(A) ahead of schedule
(B) beyond schedule
(C) as per schedule
(D) on critical path
Answer: ahead of schedule
Explanation:
Q11. The disadvantage of product layout is
(A) high initial investment for the specialized facilities
(B) skilled labour to operate machines
(C) production time is longer, requiring more goods in inventory
(D) high cost of inspection
Answer: high initial investment for the specialized facilities
Explanation:
Q12. The time of completing a project in network analysis is given by following time of the critical activity meeting at the finalitiode
(A) early finish
(B) early start
(C) late start
(D) late finish
Answer: early finish
Explanation:
Q13. Select the correct step used for scheduling a project by C.P.M.
(A) a project is divided into various activities
(B) sequence of various activities is made according to their importance
(C) network is drawn by connecting the activities and the events
(D) All of these
Answer: All of these
Explanation:
Q14. Select the correct statement from the following
(A) critical path method is an improvement upon bar chart method
(B) critical path method provides a realistic approach to the daily problems
(C) critical path method avoids delays which are very common in bar chart
(D) All of these
Answer: All of these
Explanation:
Q15. Select the correct statement from the following
(A) programmer evaluation and review technique is event oriented
(B) programmer evaluation and review technique is not event oriented
(C) critical path method is event oriented
(D) none of these
Answer: none of these
Explanation:
Q16. The first method invented for planning projects was
(A) bar chart method
(B) milestone chart
(C) critical path method (CPM)
(D) programme evaluation and review technique (PERT)
Answer: bar chart method
Explanation:
Q17. Bar charts are suitable for
(A) minor works
(B) major works
(C) large projects
(D) All of these
Answer: minor works
Explanation:
Q18. A milestone chart
(A) shows the inter dependences of various jobs
(B) depicts the delay of jobs, if any
(C) points outgoing ahead of schedule of jobs, if any
(D) none of these
Answer: none of these
Explanation:
Q19. In perpetual inventory control, the material is checked as it reaches its
(A) minimum value
(B) maximum value
(C) average value
(D) middle value
Answer: minimum value
Explanation:
Q20. Monte Carlo solutions in queuing theory are extremely useful in queuing problems
(A) that can’t be analysed mathematically
(B) involving multistage queuing
(C) to verify mathematical results
(D) All of these
Answer: that can’t be analysed mathematically
Explanation:
Related Multiple choice questions:
automobile engineering objective questions and answers part1
automobile engineering objective questions and answers part2
automobile engineering objective questions and answers part3
basic of mechanical engineering objective questions and answers part1
basic of mechanical engineering objective questions and answers part2
basic of mechanical engineering objective questions and answers part3
basic of mechanical engineering objective questions and answers part4
basic of mechanical engineering objective questions and answers part5
basic of mechanical engineering objective questions and answers part6
engineering materials objective questions and answers part1
engineering materials objective questions and answers part2
engineering materials objective questions and answers part3
engineering materials objective questions and answers part4
engineering materials objective questions and answers part5
engineering materials objective questions and answers part6
engineering materials objective questions and answers part7
engineering materials objective questions and answers part8
engineering materials objective questions and answers part9
engineering mechanics objective questions and answers part1
engineering mechanics objective questions and answers part2
engineering mechanics objective questions and answers part3
engineering mechanics objective questions and answers part4
fluid mechanics objective questions and answers part1
fluid mechanics objective questions and answers part2
fluid mechanics objective questions and answers part3
fluid mechanics objective questions and answers part4
fluid mechanics objective questions and answers part5
fluid mechanics objective questions and answers part6
fluid mechanics objective questions and answers part7
fluid mechanics objective questions and answers part8
fluid mechanics objective questions and answers part9
fluid mechanics objective questions and answers part10
fluid mechanics objective questions and answers part11
heat transfer objective questions and answers part1
heat transfer objective questions and answers part2
heat transfer objective questions and answers part3
heat transfer objective questions and answers part4
hydraulic machines objective questions and answers part1
hydraulic machines objective questions and answers part2
ic engines objective questions and answers part1
ic engines objective questions and answers part2
ic engines objective questions and answers part3
ic engines objective questions and answers part4
ic engines objective questions and answers part5
machine design objective questions and answers part1
machine design objective questions and answers part2
machine design objective questions and answers part3
machine design objective questions and answers part4
machine design objective questions and answers part5
machine design objective questions and answers part6
machine design objective questions and answers part7
production engineering objective questions and answers part1
production engineering objective questions and answers part2
production engineering objective questions and answers part3
production engineering objective questions and answers part4
production engineering objective questions and answers part5
production engineering objective questions and answers part6
production engineering objective questions and answers part7
production engineering objective questions and answers part8
production engineering objective questions and answers part9
steam engines objective questions and answers part1
steam engines objective questions and answers part2
steam engines objective questions and answers part3
steam engines objective questions and answers part4
steam engines objective questions and answers part5
steam engines objective questions and answers part6
steam engines objective questions and answers part7
steam engines objective questions and answers part8
steam engines objective questions and answers part9
strength of materials objective questions and answers part1
strength of materials objective questions and answers part2
strength of materials objective questions and answers part3
strength of materials objective questions and answers part4
theory of machines objective questions and answers part1
theory of machines objective questions and answers part2
theory of machines objective questions and answers part3
theory of machines objective questions and answers part4
theory of machines objective questions and answers part5
theory of machines objective questions and answers part6
theory of machines objective questions and answers part7
thermodynamics objective questions and answers part1
thermodynamics objective questions and answers part2
More Multiple choice questions:
Computer Science multiple choice questions and answers
Computer Science multiple choice questions and answers
Computer Science multiple choice questions and answers