The critical path of a network represents - Basic mechanical Engineering
« Previous Question
Q. The critical path of a network represents
(A) the minimum time required for completion of project
(B) the maximum time required for completion of project
(C) maximum cost required for completion of project
(D) minimum cost required for completion of project
Answer: the minimum time required for completion of project
Explanation:
Next Question»
Related Multiple choice questions:automobile engineering objective questions and answers part1
automobile engineering objective questions and answers part2
automobile engineering objective questions and answers part3
basic of mechanical engineering objective questions and answers part1
basic of mechanical engineering objective questions and answers part2
basic of mechanical engineering objective questions and answers part3
basic of mechanical engineering objective questions and answers part4
basic of mechanical engineering objective questions and answers part5
basic of mechanical engineering objective questions and answers part6
engineering materials objective questions and answers part1
engineering materials objective questions and answers part2
engineering materials objective questions and answers part3
engineering materials objective questions and answers part4
engineering materials objective questions and answers part5
engineering materials objective questions and answers part6
engineering materials objective questions and answers part7
engineering materials objective questions and answers part8
engineering materials objective questions and answers part9
engineering mechanics objective questions and answers part1
engineering mechanics objective questions and answers part2
engineering mechanics objective questions and answers part3
engineering mechanics objective questions and answers part4
fluid mechanics objective questions and answers part1
fluid mechanics objective questions and answers part2
fluid mechanics objective questions and answers part3
fluid mechanics objective questions and answers part4
fluid mechanics objective questions and answers part5
fluid mechanics objective questions and answers part6
fluid mechanics objective questions and answers part7
fluid mechanics objective questions and answers part8
fluid mechanics objective questions and answers part9
fluid mechanics objective questions and answers part10
fluid mechanics objective questions and answers part11
heat transfer objective questions and answers part1
heat transfer objective questions and answers part2
heat transfer objective questions and answers part3
heat transfer objective questions and answers part4
hydraulic machines objective questions and answers part1
hydraulic machines objective questions and answers part2
ic engines objective questions and answers part1
ic engines objective questions and answers part2
ic engines objective questions and answers part3
ic engines objective questions and answers part4
ic engines objective questions and answers part5
machine design objective questions and answers part1
machine design objective questions and answers part2
machine design objective questions and answers part3
machine design objective questions and answers part4
machine design objective questions and answers part5
machine design objective questions and answers part6
machine design objective questions and answers part7
production engineering objective questions and answers part1
production engineering objective questions and answers part2
production engineering objective questions and answers part3
production engineering objective questions and answers part4
production engineering objective questions and answers part5
production engineering objective questions and answers part6
production engineering objective questions and answers part7
production engineering objective questions and answers part8
production engineering objective questions and answers part9
steam engines objective questions and answers part1
steam engines objective questions and answers part2
steam engines objective questions and answers part3
steam engines objective questions and answers part4
steam engines objective questions and answers part5
steam engines objective questions and answers part6
steam engines objective questions and answers part7
steam engines objective questions and answers part8
steam engines objective questions and answers part9
strength of materials objective questions and answers part1
strength of materials objective questions and answers part2
strength of materials objective questions and answers part3
strength of materials objective questions and answers part4
theory of machines objective questions and answers part1
theory of machines objective questions and answers part2
theory of machines objective questions and answers part3
theory of machines objective questions and answers part4
theory of machines objective questions and answers part5
theory of machines objective questions and answers part6
theory of machines objective questions and answers part7
thermodynamics objective questions and answers part1
thermodynamics objective questions and answers part2
More Multiple choice questions:
Computer Science multiple choice questions and answers
Computer Science multiple choice questions and answers
Computer Science multiple choice questions and answers